Skip to content

Build · Project management

The job, on the record.

Every RFI, submittal, drawing revision, daily log and lookahead sits on one record. The field writes to it from the floor it is standing on, the office reads the same line, and the version history keeps the date stamp and the author attached.

Sheet · project management
Record types
14
Open RFIs
38
Median response
3.2 D
Drawing revisions
1,204
Field users
UNLIMITED
Field sync
OFFLINE-FIRST
PM · TOWER 12 · L01–L41
RECORD · 6 WAYS IN · 1 SOURCE

What's in the record

Everything the job runs on.

Six ways in, one record underneath. Nothing here is a copy of something else, so nothing has to be reconciled at the end of the month.

RFI-0047 · S-412 REV C · CLOCK 7.0D

One record

One RFI, end to end.

Scroll and the record moves. Raised on the morning walk, routed to the architect of record, answered against the drawing, closed with the frame that started it — three point two days on a seven-day clock.

RFI-0047

Slab edge detail — Level 12 north bay

Discipline structural · Spec 03 30 00 · Meridian Build Group

CLOSEDELAPSED 3.2 D / 7.0 D
Ball in court
CLOSED ON RECORD
Drawing
S-412 REV C
Schedule impact
0 D
Cost impact
$0
  1. OPEN14 MAR · 08:12

    Raised on the 07:40 ground walk. The 360 frame and the marked-up sheet attach themselves on send — nobody walks back to the trailer to file it.

  2. IN REVIEW14 MAR · 15:40

    Routed against S-412 Rev C. Two earlier RFIs on the same edge detail surface with their answers, so the question is asked once.

  3. ANSWERED16 MAR · 11:05

    Detail confirmed, no revision required. The answer lands on the drawing, the daily log and the three-week lookahead in the same second.

  4. CLOSED17 MAR · 09:30

    Closed against the frame that raised it. Three point two days, on a contract clock that allows seven.

RFI-0047 · CLOSED 3.2D · SOURCE 360 FRAMERaised in the field, closed on the record, in three point two days.
LOG-0316 · DRAFTED 06:41 · 3,412 FRAMES

Documentation

Documentation that writes itself.

The 06:05 ground walk and the 06:20 dock flight already know the weather, the crews on site, the trades working and the quantities placed. The log is drafted from them before the trailer opens.

Nothing is invented and nothing is assumed. Every field names the sensor it came from, so a signature is a review rather than a transcription. What the superintendent changes trains the draft for tomorrow.

DAILY LOG · 16 MAR 2026Drafted 06:41 · unsigned
Weather
14°C · WIND 11 KM/H · DRY

FROM SITE STATION

Crews on site
6 CREWS · 84 HEADCOUNT

FROM GEOFENCE

Trades observed
CONCRETE · REBAR · MEP ROUGH-IN

FROM GROUND WALK 06:05

Quantities placed
142 M³ · L12 NORTH BAY

FROM DOCK FLIGHT 06:20

Deliveries
3 · REBAR, FORMWORK, ANCHORS

FROM LAYDOWN YARD

Delays
NONE RECORDED

FROM SCHEDULE

Open items raised
RFI-0047 · PUNCH 12-114

FROM FIELD APP

LOG-0316 · 3,412 FRAMES · DRAFTED 06:41AWAITING SUPERINTENDENT SIGN-OFF
MERIDIAN · 41 TOWERS · DISPUTES 0

I stopped chasing paper. The log is drafted before I reach the trailer, and when the architect asks which revision we built to, the answer is on the record with a date on it.

D. Alvarez

Senior superintendent, Meridian Build Group

MERIDIAN · 41 TOWERS · 82 TRADES

56H

Saved per project manager, per month

3.2D

Median RFI turnaround across the portfolio

41

Towers running on one record

CONTACT · SALES · REPLY 1 BUS. DAY

Run the job on ground truth.

Bring us your open RFIs, your current drawing set and your worst month on the schedule. We will show you what the record does with them.